Prematurely awarded contracts increased rail cost by $354 million, auditor says

A series of “prematurely” awarded rail contracts doled out to construction companies as early as 2009 prompted delay claims and change orders that increased the cost of the Honolulu rail project by more than $354 million, according to a new report by the Hawaii State Auditor released today.

***